Eric the Mower was retrieved from Yamanto Mower and Garden Centre and was working for a few days, but has become very difficult to start since then. Instant engine starter was needed to provide ignition to start with, but is no longer working.
- Queries
- All Stories
- Search
- Advanced Search
- Transactions
- Transaction Logs
Feed Advanced Search
Advanced Search
Advanced Search
Jul 20 2021
Jul 20 2021
Timotheos closed T97: Repair 4mm extension power cable, a subtask of T45: Get power set-up for welder, as Resolved.
Timotheos moved T64: Test if Eric the Mower works from Work done, needing review to To-do list on the Trusted Contributors board.
Timotheos moved T11: Mulch flattened lantana from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos added a parent task for T114: Make list of physical signs: T115: Acquire wood for signage.
Timotheos added a parent task for T115: Acquire wood for signage: T74: Finish initial Tiny Village signage.
Timotheos added a subtask for T74: Finish initial Tiny Village signage: T115: Acquire wood for signage.
Only approximately three small black wattle trees were affected by this work. They were not of high ecological value; nonetheless, replacement trees should be organised in T112: Plant the side-banks of the Lily Pad for erosion control as a follow-up to help sequester carbon and plant up the area :)
Timotheos moved T11: Mulch flattened lantana from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T50: Install privacy door or curtains for outdoor shower from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T19: Obtain rocket stove from To-do list to Backlog on the Trusted Contributors board.
This work has been completed by Glen Lake of Bowlak Earthmoving.
Timotheos moved T109: Create Lily Pad using earthworks from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T17: Create Collaborator's Pledge Template from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T31: Create solar oven from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T109: Create Lily Pad using earthworks from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T105: Create Mailing List for Firestone Sanctuary from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T53: Level the Metal Twin cabin boxes from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T102: Replace broken light in Cottage lounge room from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T64: Test if Eric the Mower works from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T107: Fix Cottage hot water system from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T100: Investigate plans for Possum Shed from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T76: Get quotes for more large water tanks from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T97: Repair 4mm extension power cable from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T84: Install stairs onto Metal Twin 1 from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T61: Create plan for Tree House from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T14: Clear around the pineapple shed from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T102: Replace broken light in Cottage lounge room from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T98: Submit dispute in regards to failed dam from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T78: Add OpenStreetView location on sanctuary.eco from Underway to Work done, needing review on the Trusted Contributors board.
Thanks so much for fixing this @alita! Draining the fuel seems to have fixed it.
Timotheos added a subtask for T8: Add water storage onto Pineapple Shed: T76: Get quotes for more large water tanks.
Timotheos added a parent task for T14: Clear around the pineapple shed: T33: Repair pineapple shed roof.
Timotheos added a parent task for T76: Get quotes for more large water tanks: T8: Add water storage onto Pineapple Shed.
Timotheos added a subtask for T33: Repair pineapple shed roof: T14: Clear around the pineapple shed.
Timotheos removed a project from T65: Create stairway from lower road to composting toilet flat: Next Work Bee.
Timotheos moved T101: Plant Richmond birdwing butterfly host vines from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T99: Replace broken outdoor light for greenhouse area from To-do list to Complete and signed off on the Volunteer Tasks board.
Timotheos moved T101: Plant Richmond birdwing butterfly host vines from To-do list to Underway on the Next Work Bee board.
Timotheos moved T103: Install air conditioning in the Cottage from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T93: Fix Cottage sliding door flywire from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T93: Fix Cottage sliding door flywire from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T89: Clean Cottage veranda from Backlog to To-do list on the Trusted Contributors board.
Timotheos moved T93: Fix Cottage sliding door flywire from Backlog to To-do list on the Trusted Contributors board.
Timotheos moved T75: Plant bunya pine in above-road swale area from To-do list to Backlog on the Trusted Contributors board.
Timotheos moved T59: Mow around Hollow Tree Picnic Area from To-do list to Underway on the Volunteer Tasks board.
Timotheos moved T98: Submit dispute in regards to failed dam from To-do list to Underway on the Trusted Contributors board.
Timotheos added a parent task for T97: Repair 4mm extension power cable: T45: Get power set-up for welder.
Timotheos moved T51: Fix ride-on mower blades from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos moved T51: Fix ride-on mower blades from To-do list to Underway on the Trusted Contributors board.
Timotheos moved T59: Mow around Hollow Tree Picnic Area from Underway to Work done, needing review on the Trusted Contributors board.
Timotheos added a subtask for T45: Get power set-up for welder: T97: Repair 4mm extension power cable.
Timotheos triaged T96: Submit more eBird checklists and make Firestone Sanctuary a hotspot as Low priority.
Jan 27 2021
Jan 27 2021
It was potentially one of:
Investigate https://www.glassware.net.au/ which is the company that did the etched glasses I received from work :)
Timotheos renamed T85: Design the Firestone Sanctuary logo from Create the Firestone Sanctuary logo to Design the Firestone Sanctuary logo.
Timotheos added a parent task for T85: Design the Firestone Sanctuary logo: T92: Create Firestone Sanctuary logo plates.